Four accelerated projects underway

0

While the much-talked-about Padma bridge project is nearing completion with only 11% of construction remaining, the authorities concerned hope to complete the project on schedule by June of the year. next.

The Padma Multipurpose Bridge project achieved 89 percent physical progress while about 87.67 percent of project funds were spent in November, according to a report by the Implementation Monitoring and Evaluation Division. implementation (IMED) on the progress of eight fast-track projects. projects.

For all the latest news, follow the Daily Star’s Google News channel.

Shafiqul Islam, project manager for the Padma Bridge, told the Daily Star that the rest of the physical work includes installing a gas line, electrical work, forming the river and the like.

Asked about the mat of the associated approach road, Islam said that some mat has been done so far while the rest will be done later.

However, Islam went on to say that there was no possibility of completing the project before the deadline.

Construction of the bridge began in November 2014 to connect the southwestern region of the country to the capital by road and rail.

Once in service, the 6.15 kilometer long bridge will connect Dhaka with 21 districts in the southwest. It is expected to increase the country’s gross domestic product by 1.2%.

Including this project, three other accelerated projects, such as the Rampal super thermal power plant project, the deep water port of Payra and the Chattogram-Cox’s Bazar rail link are among those recording good physical progress ranging from 65% at 73% while the other four were witnesses 50 percent or less, according to the IMED report.

The Dhaka metro project, officially known as Dhaka Mass Rapid Transit Development Project Line 6, registered physical progress of 50% after spending 75.63% of its allocated funds, according to the report.

The country’s very first metro is set to begin commercial operations in the Uttara-Agargaon section on December 16 – Victory Day – next year.

Metro rail authorities will begin partial operation of the new mode of public transport with 10 trainsets, an official said.

Formerly known as the Mass Rapid Transit Line 6, the elevated rail line is being built between Uttara Sector-3 and Motijheel at a cost of approximately Tk 22,000 crore.

When completed, it will be able to transport 60,000 people per hour and will cut the travel time from Uttara to Motijheel from about two hours to just 40 minutes.

About 73.06 percent of construction on the Maitree (2X660 MW) super thermal power project at Rampal was completed in November with 71.95 percent of the project funds, estimated at Tk 16,000 crore, having been spent.

Power Development Board (PDB) officials said the plant will start producing power on a trial basis in March next year, while it could add power to the national grid from May or June.

Chattogram-Cox’s Bazar Rail Link project, Tk18,034.47 crore, saw a 65% progress in its physical works, while 33.88% of its allocated funds were spent through November, according to the IMED report.

The project aims to integrate the tourist town into a rail network and to establish connections with the Trans-Asian rail corridor.

The Rooppur nuclear power plant project in Pabna recorded a physical progression of 42.12% with a financial progression of 40.44% in November.

The project is expected to become operational from 2023, months ahead of the 2024 deadline, according to its project manager Shaukat Akbar.

Originally, the first unit of the nuclear power plant was to open by 2024 and the second unit by 2025.

Now the first unit will operate in 2023 and electricity will be supplied to the national grid accordingly, Akbar told a group of reporters in October.

The second unit will become operational six to eight months after the first unit opens, he said.

Prime Minister Sheikh Hasina inaugurated on October 10 the installation of the reactor vessel in the first reactor building of the plant.

The Payra Deep Seaport project, involving an estimated Tk 4,374.47 crore, achieved 83% physical progress and 71.24% financial progress.

Meanwhile, the Tk 39,246 crore Padma Bridge Rail Link project recorded 48% physical progress while achieving 51.82% financial progress through November, the report added.